Another Bit

10 minutes, token progress, but still managed to break another of Don's drill bits.

Monday, September 26, 2011

Framing up the wing fixture "shelf."

About 15 minutes spent on the Bearhawk after work today. Had to spend some time clearing rock and roll paraphenalia our of the work area first.

Sunday, September 25, 2011

More Wing Fixture Progress

Spent about 30-45 minutes cutting pieces for the wing fixtures, Will Fischer helping.

Sunday, September 18, 2011

Wing Fixture Fabrication, Day Two

Put together eight legs yesterday, and started working on the platform frame today.

Saturday, September 17, 2011

Wing Fixture Progress

Building wing installation fixtures. Broke Don's 1/16 bit and then decided to forget about predrilling.

Friday, September 16, 2011

Wing Fixtures and Hangar Inspection

In the process of building fixtures for installation of the wings onto the aircraft.  Because of the lengthened main gears, the bottoms of the wings mount seven feet AGL.

The plan is to finish them tomorrow before the annual hangar inspection by the fire department.